Step 1
Pre-Construction Process
- Select Lot
- Select Plan
- Design review
- Finalize Specifications & Contract
Step 2
Lot Preparation & Foundation
- House Stake Out
- Dig & Pour Footing
- Foundation & Block
- Pour Garage Slab Floor
Step 3
Framing
- Frame Floors, walls, ceiling, roof, decks & porches
- Install windows & doors
- Wrap House
- Paper Roof
Step 4
Rough-Ins
- Plumbing
- HVAC
- Electric
- Structured Wiring
Step 5
Exterior Cornice
- Cornice works begins
Step 6
Roof
- Install fiberglass shingles/metal roof
Step 7
Insulation
- Batt and Spray in Insulation
Step 8
Exterior Siding
- Exterior Siding is installed when cornice is complete
Step 9
Foundation
- Stucco or Brick Foundation
Step 10
Exterior Paint
- Paint Siding & Trim
Step 11
Sheet Rock
- Board is hung and finished
Step 12
Interior Trim
- Inter Trim & Built Ins start after Sheet rock is complete
Step 13
Cabinets & Countertops
- Installed with trim or shortly thereafter
Step 14
Interior Paint
- Paint will begin when the trim carpenters finish
Step 15
Hardwood Flooring & Tile
- Unfinished Hardwood is installed
- Tile is installed
Step 16
Landscaping
- Final lot grades
- Concrete or Paver Driveways are installed
- Patios & sidewalks are installed
- Install shrubs & sod
- Install sprinkler system
Step 17
City Inspections
- Final Inspections are performed by the City of Norfolk
- Certificate of Occupancy is issued
Step 18
Homeowner Walk Through
- Introduction to new home
- Contact & Warranty Information is provided